Transmission troubles

We're all about wind power — but do we have a way to harness green energy?
By DEIRDRE FULTON  |  February 11, 2009

090213_turbines_main
Late last month, Maine's second large commercial wind farm officially opened at Stetson Mountain in the eastern part of the state. The 38-turbine installation, which will produce power for the equivalent of 23,500 homes, was hailed by newspapers, businesspeople, and government officials as a step toward achieving the state's renewable-energy goals. Also at the end of January, a proposal to erect a wind-measurement device near the East End School on Munjoy Hill created some amount of Not-In-My-Backyard brouhaha right here in Portland.

Several additional projects and proposals are in the works, including ones in Aroostook County; University of Maine professors are at work developing offshore wind turbines that could be situated far into the ocean; and Maine was identified by the energy consulting firm AWS Truewind as having the most abundant wind-energy resources in New England. In other words, wind energy is booming business in Maine, where we are rich in both the physical resource, and the human capital to develop it.

But for all this potential, both in terms of the power source itself, and the brainpower behind it, Maine risks losing a lot of money — and, therefore, jobs — if the state can't figure out how to actually transport the power from the wind turbines to the electrical grid, and to our homes. Especially given that many large-scale wind projects are sited in rural areas, energy transmission is one of the biggest hurdles to renewable-energy development. And this isn't just a Maine issue. In The Economist last year, the American Wind Energy Association's policy director Rob Gramlich called transmission the "biggest long-term barrier" to national wind-energy expansion.

For evidence, look no further than the collapse, last week, of a major new transmission project in northern Maine. On Thursday, the Maine Public Utilities Commission sent back to the drawing board the Maine Power Connection (MPC) project, which would have connected Aroostook County power sources (such as wind farms) to the New England electrical grid via a new transmission line.

The rejection has negative implications for the 800-megawatt wind farm proposed by Aroostook Wind Energy, a subsidiary of the Texas-based Horizon Wind Energy company. Without the $625 million, 200-mile, 345-kilovolt MPC transmission line, the Aroostook wind farm will be a harder sell, says Brent Boyles, president of the Maine & Maritimes Corporation, which is the parent company of Maine Public Service Company, a partner in the project. Indeed, while Horizon Wind project development manager Tanuj Deora says the company remains "optimistic and hopeful" about the wind potential in northern Maine, he also admits that "we do have a bit of transmission hiccup," and "no project is a guarantee," meaning that the fate of the project is up in the air.

Watch for this to become a familiar refrain.

"They want to be here, but they don't have the access," Boyles says of prospective wind developers who balk at the lack of sufficient transmission infrastructure — lines that are too jammed to transport additional power, or else completely non-existent. (See sidebar.) Indeed, why would anyone want to invest in a project whose express goal is to create power — without a guarantee that said power will eventually end up helping someone turn on the lights? (And that's not an altruistic concern — if the power doesn't let someone turn on the lights, there's no money in the generation project.)

1  |  2  |  3  |   next >
Related: A win-wind situation, Earth, Air, Fire, and Water, RI goes (a little) green, More more >
  Topics: News Features , Barack Obama, Science and Technology, Brent Boyles,  More more >
| More

ARTICLES BY DEIRDRE FULTON
Share this entry with Delicious
  •   A NEW DOCUMENTARY EXPLORES IMMIGRANT YOUTH AND THEIR PLACE IN MAINE AND AMERICA  |  May 23, 2012
    "Back in the Congo, we heard rumors that America is paradise — where everything is perfect, money flows like water, you can eat as much as you want, whenever you want, you can get anything," says Emmanuel Muya, one of 15 immigrant high school students featured in a new documentary, The Whole World Waiting , which will premiere at SPACE Gallery on Thursday.
  •   THE POTENTIAL OF TEDXDIRIGO  |  May 23, 2012
    There were several impressive, stick-in-your-mind talks at the TEDxDirigo: Engage conference, held last Saturday at the University of Southern Maine.
  •   THE SECRET WORLD OF USM’S BLADE SOCIETY  |  May 16, 2012
    It's a Tuesday night at the University of Southern Maine gym and Rob Tupper is leading a small group of fencing students through an exercise that looks like a cross between a line dance and an army drill.
  •   REVIVING THE ELECTRIC CAR  |  May 16, 2012
    Electric cars — ones that are completely rechargeable and use no gasoline — are now available in Maine, in addition to plug-in hybrid electric vehicles and traditional hybrids, both of which boast higher fuel-efficiency than conventional cars.
  •   SHIPPING NEWS  |  May 09, 2012
    The loss of the nascent container-ship line in Portland's harbor last week was not just a blow to the city's desired reputation as a shipping hub — but also to the environment.

 See all articles by: DEIRDRE FULTON



  |  Sign In  |  Register
 
thePhoenix.com:
Phoenix Media/Communications Group:
TODAY'S FEATURED ADVERTISERS
Copyright © 2012 The Phoenix Media/Communications Group